Rob Taylor Report

View Original

FERC Order Granting Rehearings For Further Consideration re Jordan Cove Energy Project

On 5/18/2020, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:


Docket(s):               CP17-494-001
                        CP17-495-001
Lead Applicant: PACIFIC CONNECTOR GAS PIPELINE, LP
Filing Type:     Delegated Order
Description:     Order Granting Rehearings For Further Consideration re Jordan Cove Energy Project L.P. et al. under CP17-495 et al.

To view the document for this Issuance, click here
http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20200518-3010

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Jordan Cove Energy Project L.P. Docket Nos. CP17-495-001
Pacific Connector Gas Pipeline, LP CP17-494-001
ORDER GRANTING REHEARINGS FOR
FURTHER CONSIDERATION
(May 18, 2020)
Rehearings have been timely requested of the Commission’s order issued on
March 19, 2020, in this proceeding. Jordan Cove Energy Project L.P. and Pacific Connector Gas Pipeline, LP, 170 FERC ¶ 61,202 (2020). In the absence of Commission action within 30 days from the date the rehearing requests were filed, the requests for rehearing (and any timely requests for rehearing filed subsequently)1 would be deemed denied. 18 C.F.R. § 385.713 (2019).


In order to afford additional time for consideration of the matters raised or to be raised, rehearing of the Commission’s order is hereby granted for the limited purpose of further consideration, and timely-filed rehearing requests will not be deemed denied by operation of law. Rehearing requests of the above-cited order filed in this proceeding will be addressed in a future order. As provided in 18 C.F.R. § 385.713(d), no answers to the rehearing requests will be entertained.


Nathaniel J. Davis, Sr.,
Deputy Secretary.
1 See San Diego Gas & Electric Company v. Sellers of Energy and Ancillary Services into Markets Operated by the California Independent System Operator and the California Power Exchange, 95 FERC ¶ 61,173 (2001) (clarifying that a single tolling order applies to all rehearing requests that were timely filed).